potpisivanje-ugovora-STRABAG
12.01.2021. Grad Zabok

ACTIVITY 6: Construction of UPOV Zabok and UPOV Zlatar

On January 12th, the signing ceremony of the Public Procurement Contract was held: “Construction of wastewater treatment plant Zabok drainage system and drainage system Zlatar” within the EU Project: “Construction of wastewater collection and drainage system Zabok drainage system and Zlatar drainage system”.

The contract was concluded between the beneficiaries of the project Zagorski vodovod d.o.o. as the contracting authority and the Austrian contractor STRABAG AG, and on the basis of an open public procurement procedure of high value and an executive selection decision.

The total contracted value of the works in question amounts to HRK 157,993,937.90 without VAT. This Agreement is the last in a series of five construction contracts, the implementation of which is a key prerequisite for the successful implementation of the EU Project.

The deadline for completion of works is 37 months.

The signing of the Contract took place in the Zabok Waterworks facility.

In addition to the representatives of the Contractor STRABAG AG and the Client Zagorski vodovod d.o.o., this important event was attended by the representatives of Hrvatske vode Davor Vukmirić, Deputy General Manager of Hrvatske vode and Tomislav Suton, acting. Director of the Water Management Department for the upper Sava, then the mayors of Zabok Ivan Hanžek and Oroslavje Emil Gredičak, the mayor of Zlatar Jasenka Auguštan – Pentek and the mayor of Zlatar Bistrica Žarko Miholić, and representatives of Engineers Institut IGH d.d. and the provider of advertising and visibility services Projekt jednako razvoj d.o.o.

As part of the subject Activity 6 – Construction of UPOV Zabok and UPOV Zlatar, the construction of two devices (plants) for wastewater treatment is planned:
• In the Zabok Agglomeration, the construction of a wastewater treatment plant in Oroslavje is planned for 36,940 ES, III. degree of purification and construction of a solar sludge drying plant.
• In the Zlatar Agglomeration, the construction of a wastewater treatment plant Zlatar Bistrica is planned for 14,690 ES, III. degree of purification.

The construction of UPOV Oroslavje is planned in the area of ​​the cadastral municipality of Stubička Slatina, and the construction of UPOV Zlatar Bistrica is planned in the area of ​​the cadastral municipality of Lovrečan.