Status of works within the project: “Construction of the wastewater collection and drainage system of the Zabok drainage system and the Zlatar drainage system”, Activity II, June 2022.
Activity II includes the construction of:
• 88.7 km of gravity pipelines,
• 2.22 km of pressure pipelines,
• 27 pumping stations
• 29 overflow buildings
So far, the following has been performed:
• Activity II – LOT I – Agglomeration Zabok – Phase I, financial realization of the total value of performed works amounts to HRK 21,361,587.40, which is 11.53% of the total value of the contracted Contract for works for the subject Activity II.
A total of 17,773.75 m of collectors have been constructed on Activity II / LOT I so far, and 207 house connections have been made.