03.05.2022. Grad Zabok

Status of works within the project: “Construction of wastewater collection and drainage system of Zabok drainage system and Zlatar drainage system”, by the end of April 2022.

ACTIVITY 2 – CONSTRUCTION OF WASTEWATER COLLECTION AND DRAINAGE SYSTEM ZABOK DRAINAGE SYSTEM, PHASE I
As part of activity 2, works are underway in the following areas: G. Stubica (1 team), Sv. Križ Začretje (3 teams), Oroslavje (43 teams) and Mače (1 team). A total of 8 teams are currently working at these locations. The plan for the next period is 11 teams.
ACTIVITY 3 – CONSTRUCTION OF SEWERAGE NETWORK – AGLOMERATION ZABOK – PHASE II
As part of the activity, 3 works are performed with a total of 7 groups in the area of Zabok – 3 teams, Oroslavlje – 2 teams and Donje Stubice – 2 teams. The plan for the next period is 7 teams.
ACTIVITY 4 – CONSTRUCTION OF WASTEWATER COLLECTION AND DRAINAGE SYSTEM ZLATAR DRAINAGE SYSTEM; PHASES I I II
As part of activity 4 the works are in progress in the area of Zlatar (2 teams), Lobor (1 team), Zlatar Bistrica (1 team) and Marija Bistrica (1 team), a total of 5 teams are working.
ACTIVITY 5 – CONSTRUCTION OF UPOV ZABOK AND ZLATAR
The works are going according to plan.