03.01.2022. Grad Zabok
Status of works within the project: “Construction of wastewater collection and drainage system of Zabok drainage system and Zlatar drainage system”, by the end of December 2021.
ACTIVITY 2 – CONSTRUCTION OF WASTEWATER COLLECTION AND
DRAINAGE SYSTEM ZABOK DRAINAGE SYSTEM, PHASE I
As part of activity 2, works are underway in the following areas:
Gornje Stubice, Sv. Križ Začretje, Oroslavje and Mača. During December,
6 teams worked at the mentioned locations.
ACTIVITY 3 – CONSTRUCTION OF SEWERAGE NETWORK – AGLOMERATION
ZABOK – PHASE II
As part of activity 3, works are underway in the area of Zabok and Oroslavje.
During December, 2 teams worked at the mentioned locations.
ACTIVITY 4 – CONSTRUCTION OF WASTEWATER COLLECTION AND DRAINAGE
SYSTEM ZLATAR DRAINAGE SYSTEM; PHASES I I II
As part of activity 4, works are underway in the area of Lobor and Marija Bistrica.
During December, the works were performed by 1 team at each location.