02.03.2022. Grad Zabok
Status of works within the project: “Construction of wastewater collection and drainage system of Zabok drainage system and Zlatar drainage system”, by the end of February 2022
ACTIVITY 2 – CONSTRUCTION OF WASTEWATER COLLECTION AND DRAINAGE SYSTEM ZABOK DRAINAGE SYSTEM, PHASE I
As part of activity 2, works are underway in the following areas: Gornja Stubica (2 teams), Sv. Križ Začretje (3 teams), Oroslavje (4 teams) and Mače (1 team).
ACTIVITY 3 – CONSTRUCTION OF SEWERAGE NETWORK – AGLOMERATION ZABOK – PHASE II
As part of activity 3, works are underway in the area of Zabok (3 teams), Oroslavje (1 team) and Donja Stubica (1 team).
ACTIVITY 4 – CONSTRUCTION OF WASTEWATER COLLECTION AND DRAINAGE SYSTEM ZLATAR DRAINAGE SYSTEM; PHASES I I II
As part of activity 4, works are underway in the area of Lobor (2 teams), Zlatar Bistrica (1 team) and Marija Bistrica (1 team).