22.05.2023. Grad Zabok

Visit to the construction site as part of the Project
“CONSTRUCTION OF WASTEWATER COLLECTION AND DRAINAGE SYSTEM, ZABOK DRAINAGE SYSTEM AND ZLATAR DRAINAGE SYSTEM”

In Tugonica (Marija Bistrica municipality), on May 22, 2023, a visit to the construction site was held to present the progress of the works as part of the Project “CONSTRUCTION OF THE WASTEWATER COLLECTION AND DRAINAGE SYSTEM OF THE ZABOK DRAINAGE SYSTEM AND THE ZLATAR DRAINAGE SYSTEM”. The contractor for the contracts in question is the community of bidders: CGP d.d., NGH Grupa d.o.o. and RICO d.o.o. The work is performed by NGH Grupa d.o.o. The current implementation of the works is as follows:

LOT III:
• Collectors – 27,689.51 m (46.62%)
• Audit windows – 841 pcs (45.26%)
• Home connections – 491 pcs (32.86%)
• Pumping stations – 5 pcs (21.74%)
• Overflow buildings – 2 units (18.18%)

MARIJA BISTRICA phase I:
• Collectors – 7,041.00 m (44.59%)
• Audit windows – 236 pcs (44.20%)
• Home connections – 166 pcs (17.98%)

MARIJA BISTRICA phase II:
• Collectors – 610.83 m (11.21%)
• Audit windows – 26 pcs (14.75%)
• Home connections – 39 pcs (50%)