20.03.2023. Grad Zabok

Visit to the construction site as part of the Project
“CONSTRUCTION OF WASTEWATER COLLECTION AND DRAINAGE SYSTEM, ZABOK DRAINAGE SYSTEM AND ZLATAR DRAINAGE SYSTEM”

In Veliko Trgovisce, on March 20, 2023, a visit to the construction site was held to present the progress of the works as part of the Project “CONSTRUCTION OF THE WASTEWATER COLLECTION AND DRAINAGE SYSTEM OF THE ZABOK DRAINAGE SYSTEM AND THE ZLATAR DRAINAGE SYSTEM”. The contractor for the contracts in question is the community of bidders: CGP d.d., NGH Grupa d.o.o. and RICO d.o.o. The works in Veliki Trgovisce are performed by CGP d.d. The current implementation of the works is as follows:
LOT I:
• Collectors – 47,807.73 m (50.20%)
• Audit windows – 1,470 pieces (47.84%)
• Home connections 720 pieces (26.07%)
VELIKO TRGOVISCE
• Collectors – 4,703.00 m (59.38%)
• Audit windows – 131 pcs (65.50%)
• Home connections – 70 pcs (36.84%)