Works within the project: “Construction of the wastewater collection and drainage system of the Zabok drainage system and the Zlatar drainage system”
ACTIVITY 2 – CONSTRUCTION OF WASTEWATER COLLECTION AND DRAINAGE SYSTEM ZABOK DRAINAGE SYSTEM, PHASE I
As part of activity 2, works are in progress in the areas of: Gornje Stubice, Sv. Križ Začretje, Oroslavje and Mače. There are currently 6 teams working at the mentioned locations.
ACTIVITY 3 – CONSTRUCTION OF SEWERAGE NETWORK – AGLOMERATION ZABOK – PHASE II
As part of activity 3, works are underway in the area of Zabok and Oroslavje. There are currently 2 teams working at the mentioned locations.
ACTIVITY 4 – CONSTRUCTION OF WASTEWATER COLLECTION AND DRAINAGE SYSTEM ZLATAR DRAINAGE SYSTEM; PHASE I I II
As part of activity 4, works are in progress in the area of Lobor and Marija Bistrica. Works are performed by 1 team at each location.