03.06.2022. Grad Zabok

Status of works within the project: “Construction of the wastewater collection and drainage system of the Zabok drainage system and the Zlatar drainage system”, Activity II, June 2022.

Activity II includes the construction of: • 88.7 km of gravity pipelines, • 2.22 km of pressure pipelines, • 27 pumping stations • 29 overflow buildings So far, the following has been performed: • Activity II – LOT I – Agglomeration Zabok – Phase I, financial realization of the...

Informacije
03.05.2022. Grad Zabok

Status of works within the project: “Construction of wastewater collection and drainage system of Zabok drainage system and Zlatar drainage system”, by the end of April 2022.

ACTIVITY 2 – CONSTRUCTION OF WASTEWATER COLLECTION AND DRAINAGE SYSTEM ZABOK DRAINAGE SYSTEM, PHASE IAs part of activity 2, works are underway in the following areas: G. Stubica (1 team), Sv. Križ Začretje (3 teams), Oroslavje (43 teams) and Mače (1 team). A total of 8 teams are currently...

Informacije
02.03.2022. Grad Zabok

Status of works within the project: “Construction of wastewater collection and drainage system of Zabok drainage system and Zlatar drainage system”, by the end of February 2022

ACTIVITY 2 – CONSTRUCTION OF WASTEWATER COLLECTION AND DRAINAGE SYSTEM ZABOK DRAINAGE SYSTEM, PHASE IAs part of activity 2, works are underway in the following areas: Gornja Stubica (2 teams), Sv. Križ Začretje (3 teams), Oroslavje (4 teams) and Mače (1 team).ACTIVITY 3 – CONSTRUCTION OF SEWERAGE NETWORK –...